consortium of Advanced Engineering Solutions (TZ) and ILSHIN ENGINEERING & CONSULTANTS have signed a contract with the Tanzania National Roads Agency (TANROADS)

img

img

 

SIGNING OF CONTRACT FOR: CONSULTANCY SERVICES FOR CONSTRUCTION SUPERVISION OF NEW WAMI BRIDGE (513.5 M) AND ITS ASSOCIATED March 16, 2019 The construction of Wami Bridge is part of the Government strategy to develop its road network to support the socio-economic development of Tanzania. The existing Wami Bridge which has the length of about 88.75 meters long has steep approaches and sharp curves that have been causing difficult driving conditions and in some cases caused fatal road accidents. The Tanzania National Roads Agency (TANROADS) through M/s Intercontinental Consultants and Technocrats Pvt. Ltd. in association with M/s Apex Engineering Co. Ltd has prepared a design of the new bridge and its approaches at another location around the same area in order to arrest the current situation. Narrative Description of Project: the project involves supervision of the construction of a cast-in-situ Balanced Cantilever Bridge 513.50m long. The total
design length of the project road including structure is about 4.325 km connecting Chalinze to Segera. Due to the substandard geometry of the existing bridge caused by the complicated landscape of the area, the location of the New Wami Bridge has been proposed to be on the downstream direction of the existing structure. The project also required design review of bridge, road and associated relief drainage
structures. The review of design includes review of bridge design, review of the road design which includes vertical and horizontal alignment design,
pavement design, drainage structures, structural designs for flood control structure.

Description of Actual Services provided by your staff:
 Preparation and approval of Quality control and quality assurance plan
 Bridge design review
 Review of geometrical and profile design
 Supervision of construction of drainage structures such as bridge, box culverts and
pipe culverts
 Review of pavement design
 Mix design of stabilized material and cement concrete

Name of the Firm: Advanced Engineering Solutions

Assignment name: Consultancy Services for Construction Supervision of New Wami Bridge (513.5m) and its Associated Approach Roads (4.325km)

Location within the Country: Chalinze (Coast Region), Tanzania

Name of the Client: TANROADS –Headquartersh

Duration of Assignment: 60 Monthsp Start date [Month/year]: March, 2019

Professional staff provided by your firm: 4 No. Staff: 6 No. of Person-Months: 68

Completion Date: [Month/year]: March, 2024

Name of Associated Consultant, if any: Ilshin Engineering & Consultants [South